project includes the construction of the strengthening interventions of a three-storey
reinforced concrete building in Glyfada, Athens. It involved the strengthening
of 66 R/C columns by increasing their cross-sections with the application of
new steel reinforcement and shotcrete. Interventions were also carried out at
the foundation of the building.
The budget reached 70.000,00 euros. The construction began in June 2009 and
lasted two months.


Strengthening
a 3-storey R/C building in Glyfada, Athens