project includes the design and construction of the strengthening interventions of a three-storey
reinforced concrete building in Chalkida. It involved the strengthening
of 30 R/C columns by increasing their cross-sections with the application of
new steel reinforcement and shotcrete. Signifinant interventions were also carried out at
the foundation of the building.
The construction began in May 2011 and
lasted two months.






Strengthening