The project involves the repair and strengthening of the ground floor slab of an industrial building floor of 37.500 m² in Patras. The floor had been severely damaged, due to the settlement of the soil filling below the slab with crack opening up to 5cm. The repair was carried out on an area of approx. 20.000 m² and involved cement grouting (about 400,000 lt) below the slab to fill in the gaps and the repair of cracks of a total length of 20,000m with various methods, depending on the cracks width. It also involved changes in the 7.500m² cold storage rooms of the warehouse and various renovation works.

The burget of the project is approx. 1.600.000€ and the works that started in September 2019 are carried out gradually without suspension of the operation of the warehouse.