The project involved the removal of six columns at the façade of a supermarket store in Alimos.

The demolition was carried out with the implementation of temporary shoring to support the overlying slabs, ensuring the structural stability of the building during the works. Following the removal of the columns, permanent support of the slabs and beams was achieved through the construction of a steel frame.

The works were completed within a one-month period in early 2025, while the store remained fully operational throughout the entire duration of the interventions.