The project involves the strengthening of reinforced concrete slabs and beams at the Olympic Indoor Hall (OAKA Indoor Arena), aiming to increase their load-bearing capacity in order to accommodate additional loads arising from the construction of new suites.
The strengthening interventions were carried out using fiber-reinforced polymer (FRP) systems. Specifically, FRP wrapping was applied to enhance shear capacity, while bonded FRP laminates were used to improve flexural performance.
The total project budget amounted to approximately €150,000, and the works were completed within a one-month period in late 2025.