The project involved the construction of the infrastructure works of a 500kWp photovoltaic station in Thiva and included the the access roads, the PV strings foundations, the perimeter fencing, and the concrete constructions.
The works lasted for 45 days in January and February 2013, and the project’s total budget was 700,000.00€ – 100,000.00€ for the infrastructures.