The project includes the strengthening of the ground storey of a three-storey reinforced concrete building in Chalkida, so that to enable the addition of a new storey. The strengthening interventions involve the strengthening of existing vertical elements of reinforced concrete by increasing the cross-section with the application of new steel reinforcement, cast concrete and shotcrete, as well as the strengthening of the foundation. The project also includes the construction of new balconies and one retaining wall.
The construction began in November 2011 and lasted four months.